What does the term “punch list” refer to in construction?

Master the PE Civil Construction Exam. Prepare with quizzes featuring multiple-choice questions and comprehensive explanations. Ace your exam!

Multiple Choice

What does the term “punch list” refer to in construction?

Explanation:
The term “punch list” in construction refers specifically to a list of tasks that need to be completed or corrected before the project can be considered finished. This list typically includes items that were not completed during the main construction phase, along with any repairs or adjustments required to meet the contract specifications or applicable building codes. Creating a punch list typically occurs towards the end of a construction project and serves as a quality control measure to ensure that all aspects of the project are satisfactory before final payment is made to the contractor. It is an essential tool used by project managers, architects, and owners to ensure that every detail is finalized and meets the agreed-upon standards. The other choices represent different concepts in construction; for instance, a list of completed work for final review would not acknowledge outstanding tasks that need to be addressed, while a schedule for post-construction evaluations and a checklist for safety inspections serve different specific purposes related to project oversight and safety compliance, rather than the completion process seen with a punch list.

The term “punch list” in construction refers specifically to a list of tasks that need to be completed or corrected before the project can be considered finished. This list typically includes items that were not completed during the main construction phase, along with any repairs or adjustments required to meet the contract specifications or applicable building codes.

Creating a punch list typically occurs towards the end of a construction project and serves as a quality control measure to ensure that all aspects of the project are satisfactory before final payment is made to the contractor. It is an essential tool used by project managers, architects, and owners to ensure that every detail is finalized and meets the agreed-upon standards.

The other choices represent different concepts in construction; for instance, a list of completed work for final review would not acknowledge outstanding tasks that need to be addressed, while a schedule for post-construction evaluations and a checklist for safety inspections serve different specific purposes related to project oversight and safety compliance, rather than the completion process seen with a punch list.